Empreitada de Construção do Edifício de Comando da Nova Subestação da Ponta Delgada 30/6,6 kV
Open
The source does not publish a status. We worked this out from the opening and closing dates it does publish.
Empreitada de Construção do Edifício de Comando da Nova Subestação da Ponta Delgada 30/6,6 kV
- Status
- Open
- Procedure
- Concurso público
- Deadline
- (time not stated)
- Published
- Total budget
- €2,850,000
- Country
- Portugal
- Funder
- Eem - Empresa De Electricidade Da Madeira, S.A.
- Official page
- Open at the source portal
What applying involves
3 steps, all of them taken from this call's own documents.
Understand the call
- Read the call on the source portal and download its documents
- Check the amount you plan to request against the call's range
Submit
-
Submit before the closing date shown above
The source states the closing day but no closing time — check the portal before the last day. — calls.deadline
Similar opportunities
- Fiscalização da Empreitada de Construção do Edifício de Comando da Nova Subestação da Ponta Delgada 30/6,6 kV
- Fornecimento, Montagem e Comissionamento de Equipamentos Elétricos MT/SA/SPCC da Nova Subestação da Ponta Delgada 30/6,6 kV
- Empreitada de Conceção-Construção de uma Subestação Elétrica AT GIS 60/30 KV - 60/15 KV - 65MVA no Porto de Leixões
- Empreitada de Execução do Edifício de Exploração de Montemor-o-Novo
- Empreitada L. NORTE - PK 60 A 66 - DESNIVELAMENTOS PARA SUPRESSÃO DE PASSAGENS DE NIVEL - EXECUÇÃO
- 25EP00007373 - Ponta Delgada - PJ - Empreitada para Remodelação do edifício
Where this came from
- Source document
- https://dados.gov.pt/s/resources/contratos-publicos-portal-base-impic-anuncios-de-2012-a-2026/20260830-092820-3d797091/anuncios2026.json
- Document fingerprint
a66817bf85d37d83(SHA-256, first 16 hex characters)- Collected
- First recorded here
What has changed
- url first recorded as https://files.diariodarepublica.pt/cp_hora/2026/08/163/419970812.pdf on
- currency first recorded as EUR on
- budget_total first recorded as 2850000.00 on
- deadline first recorded as 2026-09-28 on
- published_on first recorded as 2026-08-24 on
- procedure_type first recorded as Concurso público on
- status_basis first recorded as derived_window on
- status first recorded as open on
- title first recorded as Empreitada de Construção do Edifício de Comando da Nova Subestação da Ponta Delgada 30/6,6 kV on
Data source
Fonte: IMPIC, I.P. — Instituto dos Mercados Públicos, do Imobiliário e da Construção, registo de contratos públicos do Portal BASE, via dados.gov.pt. Domínio Público — declared as `other-pd` ("Outra (Domínio Público)") by the publisher on each Portal BASE dataset.
We collected this from the source on .
The source last changed this record on Sun, 30 Aug 2026 09:28:18 GMT.